The Preliminary Scores and Project Ranking for the Round 11 Clean Ohio Green Space Conservation Program are now available. The Natural Resources Assistance Council (NRAC) met on January 12, at 2:00 p.m. to review and discuss the preliminary results.

Unweighted Scores

PRINCIPLES BENEFITS NEEDS OTHER FACTORS
RANK APPLICANT PROJECT
NAME
TOTAL
COST
NRAC
REQUEST
CUMULATIVE
REQUEST
PRSV ENH REST LKS PRVD ECON SOC ENV NDS OTH $ COOR RDN IMDY MIN
RTS
TOTAL
POINTS
1 LAND Studio Irishtown Bend Greenway Connector $2,436,200 $1,425,700 $1,425,700 7.55 8.36 7.73 9.18 9.27 9.00 9.50 7.00 9.18 4.00 9355 5.00 8.45 10.00 113.82
2 Western Reserve Land Conservancy Brecksville Upland Preserve $5,533,144. $2,213,144 $3,638,844 9.36 7.82 6.73 6.82 8.36 6.82 6.09 8.82 7.10 6.00 7.65 10.00 8.09 10.00 109.64
3 Cleveland Metroparks Preservation of Hemlock Creek Valley $250,000 $156,500 $3,795,344 86.6 8.00 6.09 8.82 8.70 6.64 7.50 8.36 7.45 4.00 7.09 10.00 6.64 10.00 108.18
4 City of Westlake Dover Ditch Stream Restoration $3,453,375 $777,000 $4,572,344 6.00 8.18 8.18 5.36 6.00 5.36 5.91 6.64 4.73 8.00 6.18 7.27 4.91 10.00 92.73
5 City of Fairview Park Coe Creek Daylighting & Stream &Habitat Restoration $442,688 $177,076 $4,749,420 5.00 7.36 9.36 4.09 2.45 4.45 3.45 7.45 5.36 6.00 7.18 5.64 6.18 10.00 84.00
TOTALS $12,115,407
$4,749,420

Weighted Scores

PRINCIPLES BENEFITS NEEDS OTHER FACTORS
RANK APPLICANT PROJECT
NAME
TOTAL
COST
NRAC
REQUEST
CUMULATIVE
REQUEST
PRSV ENH REST LKS PRVD ECON SOC ENV NDS OTH $ COOR RDN IMDY MIN
RTS
TOTAL
POINTS
1 LAND Studio Irishtown Bend Greenway Connector $2,436,200 $1,425,700 $1,425,700 22.64 16.73 15.45 27.55 18.55 9.00 19.09 21.00 27.55 4.00 9.55 5.00 8.45 10.00 214.55
2 Cleveland Metroparks Preservation of Hemlock Creek Valley $250,000 $156,500 $1,582,200 25.91 16.00 12.18 26.45 17.64 6.64 15.27 15.09 22.36 4.00 7.09 10.00 6.64 10.00 205.27
3 Western Reserve Land Conservancy Brecksville Upland Preserve $5,533,144 $2,213,144 $3,795,344 28.09 15.64 13.45 20.45 16.73 6.82 12.18 26.45 21.27 6.00 7.64 10.00 8.09 10.00 202.82
4 City of Westlake Dover Ditch Stream Restoration $3,453,375 $777,000 $4,572,344 18.00 16.36 16.36 16.09 12.00 5.36 11.82 19.91 14.18 8.00 6.18 7.27 4.91 10.00 166.45
5* City of Fairview Park Coe Creek Daylighting & Stream &Habitat Restoration $442,688 $177,076 $4,749,420 15.00 14.73 18.73 12.27 4.91 4.45 6.91 22.36 16.09 6.00 7.18 5.64 6.18 10.00 150.45
TOTALS $12,115,407 $4,749,420

*A minimum score of 156 points, 60% of total weighted points available, is required by District One NRAC to be considered for funding.

ROUND 11 ALLOCATION  $3,339,704
ADMINISTRATIVE COST $(15,000)
ROUND 10 AVAILABLE BALANCE $11,065
TOTAL AVAILABLE $3,335,769
AMOUNT RECOMMENDED $1,582,200
AMOUNT REMAINING $1,753,569


Key To Criteria:
PRSV – Preserves
ENH – Enhances
REST – Restores
LKS – Links
PRVD – Provides
ECON – Economic
SOC – Social
ENV- Environmental
NEEDS – Needs of the District
OTH $ – Other Funding
COOR – Coordination
RDN – Readiness to Proceed
IMDY – Immediacy
MIN RTS – Mineral Rights